Water, Water Everywhere
Problem:
Emergency need for replacement panelboards
The Upper Dublin Pumping Station is the source of
water for Upper Dublin Township. During a very heavy rainstorm, the pumphouse
flooded, causing all the electrical panels to burn out. The station was
able to keep pumping using auxiliary power, but it was a very limited
and expensive option.
|
|
"Penn
Panel & Box Company did a remarkable job turning the Upper Dublin
project around in 24 hours. No other supplier could have done the job
in less than 2 weeks."
Rich DiGregorio, Jr.,
United Electric Supply

|
Solution:
Two custom panelboards produced in one day
The electrical equipment distributor immediately
turned to Penn Panel & Box Company. Because Penn Panel keeps a complete
inventory of all the components needed for custom panel work, it can turn
emergency orders around in days instead of weeks. One panel had to be
sized to fit into an existing back box. The other panel and back box were
custom designed to a non- standard size. The panelboards were produced
first so that the plant could start up as quickly as possible, while the
panel door and trim were installed several days later.
Penn Panel & Box Company completed both panelboards
and shipped them within 24 hours of receiving the specifications. The
pumping station was back online using utility company power within 48
hours of the failure.

|