A Fair Exchange PROBLEM: The building was being renovated for use as office
space with a shopping center and food court on the main floor. The old
building had an antiquated electrical system, including original antique
manual switchgear for transfer between electrical services. The new tenants
of the building required an automatic switching system to comply with
codes and to make sure the building was supplied with power at all times. |
|||
|
SOLUTION: Because of Penn Panel & Box Companys recognized expertise with historic buildings, the contractor asked the company to work on the electrical design. Penn Panels experienced electrical engineers custom-designed a control scheme for automatic switching to be added to the existing equipment, much of which had been installed in the 1940s and 50s. Penn Panel pre-wired the controls for installation by the electrical contractor and sent out a field engineer for supervision of testing to ensure proper operation of the system. The final resulta beautiful historic building with all the modern conveniences, including reliable electric power, for working, shopping, and dining.
|
|||
|
| Home | Corporate History | Products & Services | Emergency Service | Office Locations | Site Map | ©
1999 Penn Panel & Box Company |
|||